News
Additional information regarding the submission of your implementation
Written on 12.12.2019 08:51 by Thomas Bock
The implementation of most of the must-have requirements (current implementation, source code, etc.) has to be pushed to the master branch of your GitLab repository. We only look at the master branch, all other branches will be ignored. Therefore, for this week's submission, make sure to push your commits to the master branch until the end of Friday (2019-12-13, 23:59).
Here is a short reminder of what has to be submitted this week (Week 8):
- The following deliverables have to be submitted to the CMS by the end of Friday (2019-12-13, 23:59):
- the progress report (incl. time log)
- an updated requirements document (as PDF). If there were any inconsistencies in the requirements document of the first milestone, they can be resolved in the updated document.
- an updated use-case diagram (as PDF). If there were any inconsistencies between between requirements and use-case diagram, they can be resolved in the updated diagram.
- an updated UML class diagram (as PDF)
- and sequence diagrams (as PDF) for, at least, six different use cases (i.e., an updated version of the three sequence diagrams from Week 6 and three additional sequence diagrams for other scenarios). All the sequence diagrams should be as fine-grained as possible, that is, they should contain concrete function/method calls with respect to the implemented functions/methods in your source code (consistent with the class diagram).
- The implementation of most of the must-have requirements has to be finished. The current implementation (source code, etc.) has to be pushed to the master branch of your GitLab repository by the end of Friday (2019-12-13, 23:59)