News

Deliverables in Week 9 & Week 10

Written on 16.12.2019 09:24 by Thomas Bock

Deliverables in Week 9:

  • The progress report (incl. time log) has to be submitted to the CMS by the end of Friday (2019-12-20, 23:59). The progress report has to contain an additional section in which the work on your issues has to be documented. In this additional section, you should place the answer to the following questions:
    •  Who worked how long on which issues?
    •  Which new issues were created? / Which bugs were found?
    •  Which issues were resolved, which bugs fixed?
    •  Which tests are already written / generated? (regardless of whether they already pass or not)

 

Deliverables in Week 10 (after the Christmas break):

  • The following deliverables have to be submitted to the CMS by the end of Friday (2020-01-10, 23:59):
    • The progress report (incl. time log). The progress report has to contain an additional section in which the work on your issues has to be documented (see also the detailed description above in the description of the deliverables of Week 9).
    • The initial test report (as PDF). The initial test report should build on your test plan and contain the current results of your tests (passed or not). Also state whether the tests discovered any errors or bugs. (It is ok to have failing tests at this point. Though, they must be documented. Don't conceal failing tests, as failing tests at this point of the project are not negative w.r.t. grading.) A coverage report is not yet necessary, it will be required in the final submission of the project in Week 12.

 

We wish you a Merry Christmas and a Happy New Year!

Privacy Policy | Legal Notice
If you encounter technical problems, please contact the administrators.